Club Matters => Road Advisory => Topic started by: AmieK on April 19, 2018, 05:08:29 PM

Title: Old School Road Reconstruction and Closure
Post by: AmieK on April 19, 2018, 05:08:29 PM
Old School Road will be closed from Winston Churchill to Heritage Rd and Mississauga Rd to Chinguacousy Rd from April 25-August 14 2018.

https://www.caledon.ca/en/news/index.aspx?feedId=3128FF83-64FD-4E32-80D2-FC0FC0ABFECD&catid=f918b98c-b9af-4094-8290-b5ea5a311ef0&newsId=4050adb7-0380-4766-bd71-f7c410d95c8d
Title: Re: Old School Road Reconstruction and Closure
Post by: Geoff Milan on April 20, 2018, 08:48:45 AM
"closed to through traffic for the duration of the project. Local access will be maintained"

Not sure if we will have access for bikes.
Title: Re: Old School Road Reconstruction and Closure
Post by: Geoff Milan on April 27, 2018, 03:03:24 PM
Old School road is now gravel west of Kennedy/Old School intersection.
Title: Re: Old School Road Reconstruction and Closure
Post by: JasonGRoth on May 07, 2018, 09:19:07 PM
Rode several sections of Old School Road this evening. Status as of 6pm May 7

West of Creditview, towards Mississauga Rd: original asphalt, construction cones at edge of road, evidence of pre-construction work in ditches on both sides of road

Between Creditview and Chinguacousy: original asphalt, construction cones at edge of road, no evidence of ongoing work at this time

Between McLaughlin and Kennedy (not part of construction notification from the region): hard packed gravel marginally improved over original horrible asphalt from just east of McLaughlin to just west of Kennedy, except for original asphalt about 150m surrounding Hwy 10 (both directions).

J.
Title: Re: Old School Road Reconstruction and Closure
Post by: JasonGRoth on June 03, 2018, 10:57:06 AM
Update as of June 3rd

Winston Churchill to Heritage - 14/10 - beautiful new asphalt, lines painted, construction done
Heritage to Mississauga - 7/10 - no construction planned or visible; road is relatively good, with minimal potholes
Mississauga to Creditview - 6/10 - old asphalt, frequent potholes, gravel over drainage culverts - but progress is being made, the drainage ditches on both sides of the road are are finished and graded; the "shoulder" is graded flat - road appears ready for new asphalt soon.
Creditview to Chinguacousy - 5/10 - old asphalt, frequent potholes, gravel over drainage culverts, the drainage ditches on the eastbound side of the road are partially finished and graded; the "shoulder" is graded flat ready for new asphalt on portions of the eastbound side; westbound side work remains in progress
Chingaucousy to McLaughlin - 7/10 - no construction is planned or visible; road is relatively good with minimal potholes
McLaughlin to Hurontario - 11/10 - previously very rough, then gravel section is now freshly paved with smooth black asphalt. Would have given a higher rating, but no lines painted yet.
Hurontario to Kennedy - 11/10 - previously very rough, then gravel section is now freshly paved with smooth black asphalt. Would have given a higher rating, but no lines painted yet.

I would say that group rides could use all of Old School except the sections between Mississauga and Chinguacousy, which should be avoided due to ongoing construction and frequent potholes. Solo riding through that section is fine, pending ongoing construction.

J.
Title: Re: Old School Road Reconstruction and Closure
Post by: Steve Maxwell on June 16, 2018, 03:38:37 PM
Section between Creditview and Chinguacousy is now paved, however there are three unpaved sections each about one meter long.
Title: Re: Old School Road Reconstruction and Closure
Post by: clair on June 17, 2018, 08:50:31 PM
Love your road rating Steve!

Not sure if you knew that WC is unpassable (we had to walk our bikes down the hill :(
at 10 Side Rd to Guelph St.